Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what"s the formula to find the quantity (consumption) of
cement,sand,aggregate for 1m3(1:2:4)?

Answer Posted / ranjithkumar.t

M15= 1:2:4 (for 1 m^3)

1m^3 = 1440kg, 1 bag = 50 kg

so, 1m^3 bags=1440/50
             = 28.8 bags 

   Cement = 1/7*1.52*28.8
          = 6.25 bags 

   Sand   = 2/7*1.52
          = 0.434 cubic meter

Aggregate = 4/7*1.52
          = 0.868 cubic meter

Is This Answer Correct ?    6 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

strength vs shape factor

2562


What is the crank length in the slab?

1081


What is Grid floor and mention its advantages ?

3251


If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.

2394


Curvature ki quantity kaise nikalte hai pls give me ans... curvature canal ka hai

3072


What applicable rate of wct in bihar

1846


I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.

6092


How will drive weight formula for circular cylinder steel bar in kg/ m please step by step drive?

2212


What are the RISKS during the project construction?

2305


manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.

2086


in one SQM plaster how much Cement and sand consumed in ratio 1:4

2245


Define What is rigging?

1105


What do we mean by partial moment release ??

3907


natucher of concrete &type of concrete?

2431


What is hybrid foundation?

1132