Answer Posted / dev
1.When you create a BOM for any material for any BOM usage the first alternative BOM will be created
that is 01.
2.Suppose if the same product can be produced using 2 different BOM's then you can create 2 BOM's
for that product,that's 2 alternative BOM 01 and 02.
3.This 2 alternative BOM's can be created for a different validity dates or lot sizes and it can be
assigned to a production version.
4.Always the first alternative BOM will be picked by the system during MRP run if they have same
validity dates and lot size.
5.In some case one BOM will be used for inhouse production and the other one for sub-contracting
purpose.
Is This Answer Correct ? | 10 Yes | 0 No |
Post New Answer View All Answers
Explain DMR.
what are Standard keys
Overlapping and splitting, where do you assign?
What are sequence, parallel, overlapping, splitting and where can we assign these
What is the planning horizon?
Can’t one material be assigned to more than one operation in a routine?
What is requirement class and requirement type?
Explain the Difference between the Discreet and REM.
What is the use of infogroups?
What are the different type of BOM usage?
What is costing? How it is affected the pp?
What is meant by payscale structure? How did you configure payscale structure?
Mention what are the types of master views for production and planning?
What is MTS and MTO and the difference between them?
what do you mean by opening periods