Answer Posted / dev
1.When you create a BOM for any material for any BOM usage the first alternative BOM will be created
that is 01.
2.Suppose if the same product can be produced using 2 different BOM's then you can create 2 BOM's
for that product,that's 2 alternative BOM 01 and 02.
3.This 2 alternative BOM's can be created for a different validity dates or lot sizes and it can be
assigned to a production version.
4.Always the first alternative BOM will be picked by the system during MRP run if they have same
validity dates and lot size.
5.In some case one BOM will be used for inhouse production and the other one for sub-contracting
purpose.
| Is This Answer Correct ? | 10 Yes | 0 No |
Post New Answer View All Answers
In project the customization is comes under which phase?
a company needs 12 standard values. how it can be maintained?
Explain the planning steps for 100 products?
Explain customer Independent requirement .
Standard mrp steps
What is the standard info set?
Explain how ‘pp’ is ‘integrated’ with other modules?
In tm, if a group of employees gets 10 days of annual leave, what will be the time evaluation status?
What is Inspection Points?
how many times pcc can run for one material?
Explain Planning file entry.
Can mrp be carried out for one particular level of a bom ( level code : 0001/0002 etc)?
What is Phantom Assembly?
If u maintain sub-contacting where and how will be reflect
Difference between Routing, Ref op set, Rate routing and Ref rate routing.