how to calculate 1:1.5:3 ratio concrete cement, sand, metal
and water please give me brief calculation
Answer Posted / sunil notiyal
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg
For 1m3 of M20 (1:1.5:3)
Broken stone = 0.856 m3
Sand = 0.472 m3
Cement = 8.22 bag
| Is This Answer Correct ? | 27 Yes | 8 No |
Post New Answer View All Answers
Which stone is best for wall construction Laterite Stone or Cement Blocks
how to determine H- zone in a column? where it will occur?
how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.
Give me an example of a time when something you tried to accomplish and failed.
how gradation of aggregates effect on slump of fresh concrete?
what will be price of 1:2:4pcc per kg?
How cracks in concrete can be avoided?
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
What is rate of concrete surface rendering work per sqm
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
is basic cost of the material includes tax?
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
How to do base isolation using ETABS software?
what is the water cement ratio for plastering
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2