concrete cube strength if fail 1 no in 7 days .What is the
solution
Answer Posted / deoghar
If 07 days concrete fails then ,it does not mean that concrete strength is poor ,7 days result is just a check of quality of concrete.Test 28days result.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L
How we calculate the service time of buildings
Which IS Code/American Code applied for coupler test of steel
How do you calculate the power of centrifugal pump?
sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you
Formula for calculation volume of essentric footing
2nd and 4rt angle elevation used in which country ?
Which is the direction for positive angle?
What are the uses of groynes?
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard
Explain what is structural frames or systems?
show answer/calculate mix 1:2:4 ratio -cement-sand -metal-water
How to compute minimum number of columns required for a site from area of site?