1 cft of brickwork 1:6 mortar ratio need 12 numbers of bricks so find the quantity of sand and number of cement bags
Answer Posted / sunil jain civil engineer katn
CEMENT AND SAND 1:6 BRICKS WORK IN USE
CEMENT 58 KG PER/CUM ( 1CUM = 35.28 CFT)
SAND 0.243 CUM PER/CUM (1 CUM =35.28 CFT)
CEMNT 58/58= ANS.1.64 KG PER/CFT QFT BRICK WORK
SAND 0.243x35.28=8.5 PER/CUM
8.5/35.28= ANS..24 CFT PER/QFT BRICK WORK
| Is This Answer Correct ? | 3 Yes | 4 No |
Post New Answer View All Answers
What is unit weight of normal concrete?
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
density of crush sand & crush stone or grit powder
Which brick is best for construction ,either fly ash or AAC BLOCKS
Material calculation of cm 1:6 for 1sqm
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3
How much 1 cum of M15, M20 & M25 concrete weigh?
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
how much quantity of cement,sand and water required for 1 sq feet flooring work .
what r the precaution for high in atp tempareture,low in atp tempareture
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
Where is the worlds longest elevator and how long is it?
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???
Define What is rigging?