proportions of m10, m15, m20, m25, m30, m40, m45, m50, m60,
m70, m75, m80 etc
Answer Posted / biswajyoti mukherjee
M10= 1:3:6
M15= 1:2:4
M20= 1:1.5:3
M25= 1:1:2
M30= 1:1:1.5
M35= 1:1:1
M40= 1:1/2:1
| Is This Answer Correct ? | 100 Yes | 24 No |
Post New Answer View All Answers
How to calculate density of 40 mm coarse aggregate, in mixing ration 1:1.5:3? Please explain calculation for density
What are advancements in civil engineering?
why the cracks occurs in NP3 class Hume Pipe ? And what is bearing capacity of it?
what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?
what is right & short method of measurement of slab&beam
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor
how to compute slab reinforcements on step by step procedures??
in the earthquqke the profile of water on dam is parabolic or not
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level
For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)
In Rcc ratio calculation I wanted to know quantity of Steel also.
Define What is rigging?