Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

HOW MANY CEMENT BAGS ARE REQUIRED IN 1 CUBIC METER

Answer Posted / naveen pandey

No. Of cement bags required depends on grade of concrete
But if talking about no. Of bags to accommodate 1cum volume,
Density of cement is 1440 kg/cum, weight per bag is 50kg
So 1440/50 = 28.8 bags

Is This Answer Correct ?    10 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

why does the most of civil engg is not intersted to going for teaching field?

2020


What is the number of IS code of practice to be followed for hydraulic design of sewerage pipe line?

2574


how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.

2021


a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer

2508


How to increase a bearing capacity of soil?

1064


can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?

2522


Any strength is a stress but any stress is not strength

1735


All aptitude question of Bechtel

1836


I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.

2203


What is the difference between chamfer and fillet?

1378


please briefly explain calculating or estimating steel quantity for a RCC column?

1898


What is the difference between built area and super built up area?

1165


how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour

1529


Pls provide me with the calculation or codes related to de- shuttering of flat slabs

6759


how to estimate costing from quantity givin in BOQ and according to this how we fill tender and final rate for perticular work.....?

2006