brick work with 1:6 cement mortar how many bricks and
cement and sand require for 1cum
Answer Posted / feedly244
if brick size 240mm*115mm*71mm
so =0.00195cum
for full wall 25%(0.25)of mortar required
for half wall 30%(0.3)
if full wall means
req bricks=1-(1*0.25)=0.75cum
so=0.75/0.00195=384.6 no of bricks
req cement=0.25/(1+6)=0.0357cum
so=0.0357*1440=51kg
req sand=0.0357*6=0.214cum
note:prepare 15% extra mortar bcoz of voids presented in sand
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
what is column foundation
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
You have 3 snd sample of different FM=0.21,FM=0.95,FM=2.90 which one is suitable for a)plastering on R.C.C b)plastering on masonary wall c)concreting column d)concreting of bored pile.also justify your answer.
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
how many minimum admixtures are used in water froofing structures
punj loyed and sapurjl palanjl
Why you are leaving present job?
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?
What is the number of IS code of practice to be followed for hydraulic design of sewerage pipe line?
how to calculate testing date
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
how to calcualate the amount of stone,cement,sand required for 1cum of 450mm thick ruble stond masonary with ratio1:5, please me an answer with dtailed step
what is the maximum number of course that can be laid according to IS code and the max height.