brick work with 1:6 cement mortar how many bricks and
cement and sand require for 1cum
Answer Posted / feedly244
if brick size 240mm*115mm*71mm
so =0.00195cum
for full wall 25%(0.25)of mortar required
for half wall 30%(0.3)
if full wall means
req bricks=1-(1*0.25)=0.75cum
so=0.75/0.00195=384.6 no of bricks
req cement=0.25/(1+6)=0.0357cum
so=0.0357*1440=51kg
req sand=0.0357*6=0.214cum
note:prepare 15% extra mortar bcoz of voids presented in sand
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
Calculate the maximum allowable speed on a horizontal curve of radius 350m if the maximum allowable values of the lateral coefficient of friction are 0.14 and the rate of superelevation is 0.08.
Differentiate first angle & third angle projection?
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal
What is meant by cad?
what is called the inverd level of mabhole chamber?
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
water leak detection system question & answer
What is the standard specification of MOR and Water Absorption of Homogenous Ceramic Floor Tiles?
Which tests are performed on soil to decide the type of foundation to be provided.
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
what is castigliano theaorem
B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS
What is the purpose of Chipping in the heavy foundation?
What is meant by dimensioning?
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar