Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step

Answer Posted / vipin kumar

Bricks=1/volume of 1 brick

1/.23*.115*.075=504 Nos of Bricks.
But Pricitaly=475 to 485 Nos of bricks(kyoki fat layer not proper 10 0r 12mm).

Sand&Cement =100 cum B/work in 30 cum sand,
Than
cement ratio=1:5
.3/1+5=.05cum dry mortar
(1beg cement volume=(1/28.8)=.0347
Than Cement=.05/.0347=1.44 Bags
Sand =.05*5=.25cum.

Is This Answer Correct ?    28 Yes 12 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the use of extruded feature in solidsworks?

1306


what is the mode of method of face bar measurement

2674


what is m30 in concrete tiles

2415


how we check the thickness and line of ceiling plaster.

2733


Explain the mechanism of cavitations in pipes and drains?

1170


Different sizes of Hollow blocks and its weight. Thanks.

2470


what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.

2801


what is civil all interview questions

2901


In Rcc ratio calculation I wanted to know quantity of Steel also.

1769


What is the general specifications of a bituminous pavement road?

1743


Forces in a Shear Wall are in plane or out of plane ?

1184


sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.

2033


WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?

2522


calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick

1860


from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar

4708