IN OLTC we observed "OUT OF STEP" Alarm, we have two
different transformer, when both are in parallel this type
of alarm observed. what's the meaning of this alarm and why
it occurs???
Answer Posted / nasseem
Out of step means that the Two transformers at different tap.
i.e. TR-1 at tap n and TR-2 at tap n+1 or n-1.
And as you know the two transformers should have same tap
"if the two transformers have same tap size i.e 1.25% for
example" when it operated in parallel to prevent the
circulation current between the two transformers.
So it seems in your case if we assume TR-1 is master and
TR-2 is follower TR-1 change its tap position while TR-2
still at it is original tap.
| Is This Answer Correct ? | 13 Yes | 0 No |
Post New Answer View All Answers
Explain about technical and non technical losses in distribution system?
what are inherent currents?
Earth has zero potential then what would be the neutral potential ?
How to calculate cable size in HT AND LT
what is the difference b/w ground & virtual ground?
how we calculate torque ? how we improve it ?where torque will either motor or generator ?
What is Negative Potential Bias
Hi Suppose we have a wye/wye transformer which is grounded at both sides,in this situation, do we have ay ground transformer? in other words, ground transformer can do any thing more (while we have nuetral wire in both sides)? As the last question, what about 3rd harmonic? we have two choices: first using wye/delta transformer + ground transformer and second using wye/wye earthed connection.in the former choice, we dont have 3rd harmoonic at the secondary side but what about Yn/yn conection? do we suffer from 3rd harmonic in the Yn/yn connection?
How to calculate KVA/VA rating of PT or CT from primary & secondary voltage or primary & secondary current?
can u give me a brief idea about power line carrier communication ??
What is Tachometer used to measure?
what will happen if earth of 33 kv cable (earthed system) is not connected to earthing pit?
HOW WE CAN REDUCE THE CIRCUIT COMPLEX OF STAR-DELTA STARTER .BECAUSE NOW WE USING ONE TIMER RELAY & THREE CONTACTOR FOR MAIN,STAR & DELTA ?IF ANY IDEAS PLZ POST.THANK U
What are the effects of electrical faults?
what is the significance of terminal voltage and phase sequence in the operation of paralleling of two generators?