How to calculate cement required for m20,m5 grade
Answer Posted / ramesh kumar
ANY RCC 1 M3 CONCRETE REQUIRED 20 MM METAL- 0.9M3
M20 MIX- 1: 1.5 : 3
3 PART OF METAL - 0.9 M3
1.5 PART OF SAND - 0.45 M3
1 PART OF CEMENT - 0.45 / 1.5
- 0.3 M3
1 M3 CEMENT - 1440 KG
0.3 M3 CEMENT - 1440*0.3
-432 KG = 8.64 BAGS
| Is This Answer Correct ? | 7 Yes | 3 No |
Post New Answer View All Answers
How to determine spacing of bars in slabs or beams
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
for pretensioning which will yield first and same for post tensioning?
What is braced excavation all about?
Sir how to find cutting length for footing steel bars in the shape of "u"
brickwork labour rate per cum ?
what is the weight of 10mm,20mm,40mm aggregate
What is the meaning of soil reinforcement?
What is meant by autocad?
What is the difference between Hinged and pinned in Column ends
can you provide a link for manual design of building?
how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing
Explain major difference between auto level and dumpy level?
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
How much cement will require for 1Rmt Skirting laying