Calculation Method
Plastering with CM 1:5 12 mm thick - 10 m2
Area to be Plastered = 10 m2
Thickness of mortar Layer = 12 mm = 0.012 m
Volume of mortar required = 10 x 0.012 = 0.12 m3
Add 15 percent allowance for undualation of surface & wastage = 0.018 m3
so, total volume of Mortar Required = 0.138 m3 say 0.14 m3
sand required for 0.14 m3 of CM 1:5 = 0.14 m3
cement required for 0.14 m3 of CM 1:5 = 0.14/5 = 0.028 m3
wt of cement required = 0.028 x 1440 = 41 kg
| Is This Answer Correct ? | 24 Yes | 24 No |
Post New Answer View All Answers
brickwork labour rate per cum ?
what is the basic difference between Coloumn & Shear Wall
Ratio for 4500 psi concrete
Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
What is the Maximum %age of Steel in columns and beams ?
What is the use of offset command?
List out some of the checking’s, done at the completion of construction?
what"s the sort of beams?
how much cement sand n bricks required in im3?and how much in plaster?
What are new methods /technologies of pothole patching?
What are the different softwares used for cad?
The mixture of different ingredients of cement is burnt at?
How to find CN by using arcgis 9.3?
what is grade intersection?