WHAT IS THE LAP LENGTH FOR COLUMN WITH DESIGN MIX M-35 RCC
Answer Posted / ravikumar nagineni
as per iS-456 this is depending on grade of concrete and
also grade steel
i.e.,
ex:-grade of concrete -M35
Grade of steel-Fe415
bars are deformed
Then development length 26.55d
where d=dia of bar
Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
Suppose a new brick wall is being constructed,and the courses and not aligned horizontally,what negetives can it cause?
What is binding spacing of the rebars at lapping zones.
how to calculate steel for slab or footings?
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
Define What is Civil Engineering?
How foundation is designed, Column design and beam design
why is the column design?
quantity of material needed for rubble stone masonry for 1:4 and 1:6
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
Define What materials were used to build the Golden Gate Bridge?
What is the cemnent ratio
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
Normally in slabs, steel quantity is not added when you calculating concrete quantity for that slab, why it is not added ?