What is the harm if we install primary side 11 KV VCB at a
distance of one Km from the 11/3.3KV 12.5 MVA transformer
through 11 KV cable.
Answer Posted / darklord
No immediate harm ,but during maintenance this 11kv line
between VCB and transformer need to be discharged with out fail,
Also during switching action their would be switching surge
created due to oscillating of wave between vcb and
transformer which will heat and may damage insulation of
transformer.
Their would also be control voltage drop for 1000mtr wire
which will have significant effect on protection of transformer.
but proper control strategies will sort this problem
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Why do we need a separate control desk & PLC control panel in Boiler plant or coal handling plant? Can we provide cost effective Control desk cum PLC panel. Is there is an specific need for control desk.. kindly advice.
what should be the no load current for 3 phase ac motors ranging from 5 kw to 1000kw?
What is evaporator & condencer & compressor
draw a circuit diagram connecting transformer OLTC- RTCC- VCB-Marshalling Box otherwise Explain in words
1. A bomber drops a bomb from an aircraft flying at 2000 km/hr. at an altitude of 7km. The speed at which the bomb will strike the earth would be
Why i receive the GCU fault in my DG Sychronization panel . what all the factors considered for this fault .
What is Servo Ventilated Motor?
-What shall be short circuit current of LV switchgear for a 1000 kva, 11.415kv, 3 phase tranformer with 5% reactance.
which pump used in STP
What is order of the system?
A commercial Building is designed with 14th floor levels with indoor substation of three phase transformer with rated capacity of 1000 Kva.The transformer delivered 65% of its rated capacity at 0.67 power factor lagging.Because of low power factor, the power customer was penalized and certain cost was charged accordingly based on every point percentage lower than 85%.This situation may repeatedly happen on the succeding energy bills of power customer.The power customer is desired to improve its historical power factor of 0.67 lagging and no further penalty be impose by the local power company on the next bill. Q: Identify the appropriate solution you want to offer to Client?.Justify SCIENTIFICALLY and MATHEMATICALLY the principles behind the solution.
what is zinc diffusion?
How shall i select the value of capacitor or inductor in a system?
what is a bus post insulator? explain its application in a substation.
Is a direct shorth ciruit on a branch MCCB in a Low Voltage Switchboard a correct means of tesing the performance for discrimination?