.What are the equipments should run when there is a black
out in power plant.
Answer Posted / sengar kunal
For Turbine, DC Emergency Oil Pump should run to lubricate turbine and generator bearings till turbine fully coasts down safely and after coasting down STG Turning gear should be switched on.
| Is This Answer Correct ? | 10 Yes | 0 No |
Post New Answer View All Answers
How to calculate power press toneage
how to differentiate between "ALL fuel lost" and "All Fuel Lost" in Boiler MFT condition?
what does mean by kva rating
can dp type level transmitter work in under vaccum condition
some one can tell me how residual type excitation is provided through transformers to an AC generator without any battery or PMG&excitor
By any way can we increase the B check hours from 300 to 500
what is the difference between compensated & normal drum level in boiler drum?
can u please tell me how to calculate the concrete quantity for a under reamed pile? r=300mm,depth=3m for a cylinder and for bulb l=.750mm,width=.525
We have Demin Closed cooling water system with expansion tank for cooling oil system. Expansion tank having N2 bladder. Whenever N2 bladder bursts out, Closed cooling water circuit pressure drops and make-up happening, eventhough there is no leaks. And how Circuit pressure drops?
explain how the third harmonic content of the magnetising current affects transformer design
im try to calculating seawater flow required for SW-FGD system. I need a guide, equation or method to do it, can some one help me! Thanks very much
What is surging in a centrifugal compressor ? How it occur's ? How is antisurging done ?
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon
Which will have more strain energy 1.Spring 2.Circular disc 3.Solid square plate.