In footing (mat) if two different dia of rods are to be used
which rod should be placed at top and bottom ( eg. 10mm &
16mm dia rods)
Answer Posted / babu lal nayak
16mm dia bar laid at bottom parallel to short span & 10mm dia bar at top parallel to long span.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
what is the exact dia of 8swg and 10swg gabion wire
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
specifications of fe500 steel
how to calculate the steel in 500yard
How to calculate ventonite bag in pile ( pile depth 25 m dia 1m)
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
i) Distinguish between Theodolite and dumpy Level? (Marks-8) ii)Distinguish between Viscous and Turbulent flow? (Marks-8) iii) Distinguish between nominal and design mix? iv) What is standard sand? v) Explain the term plane stress? Vi) Differentiate between principal plane and principal axis? Vii) write short notes on Elastic limit of structural steel? viii) Write short notes on stress concentration? ix) write short notes on "Grading of Sand" ? x) How many grades of concrete are there under standard concrete?
quantity of sand and cement for 10m2 plastering 10mm thick for the ratio of 1:4,1:3and its leabour data
Why should appointment store person for project ? what is the benefits for company ?
What in your past experience or education prepares you for the position for which you are applying
How much for the BRC lapping in full yield and half yield < and which table to get it ?
why the openings of sieves are square io size?
How much is the cover for slab?