Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Which IS Code describe the industrial flooring?

Answer Posted / m i khan

IS 13026:1991 Specification for bitumen mastic

IS 15193:2002 Code of practice for laying of pitch-mastic
flooring

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to calculate material and labor required for 100 m2 plaster?

1921


Why is the statue of liberty made of copper?

1158


What is portland cement

8211


How to determine spacing of bars in slabs or beams

2508


1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...

2089


which has high compressive strength between hollow block and brick masonry?

2423


What is capicity of cap lock scffolding stander(vertical member) and ledger of different size?

2611


What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.

2138


what does the grad of cement shows (denotes)?

1662


For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?

2264


how much repeitation for conventional and maivan formwork?

2049


what is the construction cost for per cft of multistorryed building in kolkata?

2305


Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?

1869


what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet

1644


What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil

2806