How can we calculate the cement Quantity in M25?

Answer Posted / er. sagar tiwari

M25=1:1:2

ratio=1+1+2=4

for 1 m3 (density of cement=1440kg/m3)

1/4*1.57=0.392*1440=565.2kg/50=11.4bags

(weight of one bag of cement=50kg)

another one method=

for 1 m3

ratio=1+1+2=4

1*1.52/4=0.38*30=11.4 bags (vollume of one bag of cement in

m3=1.52)

Is This Answer Correct ?    4 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.

1962


What is critical path method (c.p.m)?

709


please, what is the required bar for a column of 6mx6m the dept is 405mmx300mm,its an axially loaded ?

1165


what is the painting co efficient of slope roof tiles?

1452


I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?

1682






5. Do you feel that your present employer estimates your full work potential? Are they pleased with your work performance?

8497


insted of bentonite we can use any alternate material in piling ?

1716


what is tension footing?

1547


how we calculate the vol.of wet concrete..?

1423


With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr

1956


quantity of sand and cement for 10m2 plastering 10mm thick for the ratio of 1:4,1:3and its leabour data

2752


States some of the tool bars used in cad?

687


What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster

1858


How much cement,sand,bricks and water needed for 1square metre brick work?

1349


Prepare a Schedule for a Highrised building from starting stage to Handover?

1504