what is the minimum cement content for rcc as per is code
Answer Posted / abhijit pawar
Note : Minimum Cement Content as Per IS 456 is 280kg/m3
& Maximum 400 kg/m3
(Ref IS 456 Pg 19)
| Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
which red: used in roof teping, then use only cement
What will be the exam pattern and syllabus for j.e post of haryana staff selection commision? Advt no. (02/2015) Some people says it would only be objective type question papers while others say it would be same as ssc (1 objective,1 conventional) ?? Please answer this question it is needfull to all.
What is Architect-Prepared Contract?
what is the difference between replacement of cement by groundnut shell ash
what is difference between fluidity and workability also how palsticizer works
what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
what is the meaning of degreasing of the euipment or line.
How are freeway bridges built?
on what basis the partial factor of safety are decided? form the load combinations
how to tie 10 legged stirrups
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)