How can we calculate the cement Quantity in M25?
Answer Posted / ravindrarana8421
M25 = 1:1:2
Dry volume = 1 + 1 x 50% = 1.5
Additional Ratio = 1+1+2=4
Cement = 1.5/4 x 1 = .375 x 1440 = 540kg = 10.8 Bags/ cu m
Density of cement = 1440 kg / cu m
| Is This Answer Correct ? | 20 Yes | 7 No |
Post New Answer View All Answers
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 600 microns?
Explain the difference between shear and tensile strength.
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
how many monpower required for 1 sqm normal RCC structure ( includes finishes & MEP )
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
in 2 way slab can additional compressive reinforcement can be provided if yes than in which conditions it is required ?
How do we determine the specific gravity of a cement?
States some of the tool bars used in cad?
Explain what is change order request?
How do you calculate load bearing capacity of a waffle slab?
Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..
what is the effect of duration of earth quake on framed structures ?
at which depth the construction of tunnel is economical from cost and engineering aspect.
"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.