How can we calculate the cement Quantity in M25?
Answer Posted / ravindrarana8421
M25 = 1:1:2
Dry volume = 1 + 1 x 50% = 1.5
Additional Ratio = 1+1+2=4
Cement = 1.5/4 x 1 = .375 x 1440 = 540kg = 10.8 Bags/ cu m
Density of cement = 1440 kg / cu m
Is This Answer Correct ? | 20 Yes | 7 No |
Post New Answer View All Answers
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
what is the minimum compressive strength of clay brick
How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
why do we provide haunches in rcc box or underpasses?
How much does the leaning tower of pisa lean?
Any strength is a stress but any stress is not strength
at which depth the construction of tunnel is economical from cost and engineering aspect.
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band
How to hide dimensions in autocad?
what is the mix design for M:60 with micro silica andmetakaoline?
How can we make a hole in a solid rectangle using solidsworks?
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––