how do understand the plinth beam croos section diagram
Answer Posted / sjtbehera
Most soil conditions and building loads can be managed with
normal 1:2:4 plain concrete (PCC), which is good in taking
compression.
Steel, specially reinforced, is best to tackle tension,
which does not prevail much at the wall bottom.
It's the sheer wall load that needs to be transferred to the
foundation; as such, 4” thick plinth concrete is adequate.
As a cost-effective measure, reducing plinth concrete width
to the wall thickness, say 9” only instead of it being twice
the width at 1'6” is feasible, if appropriate conditions
prevail.
Uneven settlement
If so, why are the RCC plinth beams required? In soft and
water-logged soils, if the earth settles downwards, the
plinth may face uneven settlement.
In RCC frame structure, plinth acts as a tie, as a beam at
ground level itself. More recently, after few disasters we
have faced, RCC plinth beams are being recommended for their
earthquake-resistant properties.
In case of boulder-packed foundation in loose soil, RCC
plinth is advised to ensure proper load transfers. It is
obvious then that we should not question RCC plinths, but
question their wasteful application where not necessary
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
What is the Null Point of chimney in Power Plant
what is the permanent solution applied for restoration of leaning tower of pisa?
I have to design brick column and footing (note: without any reinforcement). Can somebody post me the design or suggest a book where i could possibly find the design? Plz help very urgent
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
What is Critical path in Ms-Project ?
what is high type road and low type roads
How to construct a water sump in a rocky soil?
Basic civil interview questions
what is the service corridor?
Formula of mid span bar
Define What are the reasons for geotechnical site investigations in Uganda?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
How does a traffic light signal work ?
why is the column design?