how do understand the plinth beam croos section diagram
Answer Posted / sjtbehera
Most soil conditions and building loads can be managed with
normal 1:2:4 plain concrete (PCC), which is good in taking
compression.
Steel, specially reinforced, is best to tackle tension,
which does not prevail much at the wall bottom.
It's the sheer wall load that needs to be transferred to the
foundation; as such, 4” thick plinth concrete is adequate.
As a cost-effective measure, reducing plinth concrete width
to the wall thickness, say 9” only instead of it being twice
the width at 1'6” is feasible, if appropriate conditions
prevail.
Uneven settlement
If so, why are the RCC plinth beams required? In soft and
water-logged soils, if the earth settles downwards, the
plinth may face uneven settlement.
In RCC frame structure, plinth acts as a tie, as a beam at
ground level itself. More recently, after few disasters we
have faced, RCC plinth beams are being recommended for their
earthquake-resistant properties.
In case of boulder-packed foundation in loose soil, RCC
plinth is advised to ensure proper load transfers. It is
obvious then that we should not question RCC plinths, but
question their wasteful application where not necessary
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
what mean By core Billing
Define What is passive earth pressure ?
why demand factor less then 1 ?
I need model question papers for writing the Dubai municipality exam,for G+1
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
how we calculate the vol.of wet concrete..?
In which code the the maximum height of concrete casting has been explained
All aptitude question of Bechtel
What is componsation
why we use aggregate,sand with cement in concrete?
What is the difference between undo & redo?
Process of pcc in wateredug
Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions