how much brick,cement,and sand required in 1cum
brickwork(1:4)
Answer Posted / er. anil kumar
brick size - .23*.115*.075
1 cum dry volume of mortar- .30
mortar ratio -1:6
for cement-.3*1/7 =.042cum
1 cum of cement - 28.8 bags
for cement- .042*28.8= 1.23 bags
for send - .30*6/7= .257cum
| Is This Answer Correct ? | 7 Yes | 11 No |
Post New Answer View All Answers
What are the different softwares used for cad?
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
2nd and 4rt angle elevation used in which country ?
What is the quantity of cement in mix m20 concrete?
how many type of admixtures for water stored structure?
Explain creep?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
can any one tell me in detail footing estimation .. i am new here in dubai so facing lots of problem...
How is improve my knowledge in construction industries....
how much of the strength comes from post-production curing
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
do we decide reinforcement steel , based on bending moment ? give example with continous slab?
What are some structures that may be subjected to fatigue?
rate analysis for cement pointing 1:4 , for 100 sq m
What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?