Sitrans LR460 Radar level
transmitter getting level
out or disturbed level
during moisture present in
the material ie coal in
the pccb bunker in CHP.Any
suggestions for this
problem...????

Answer Posted / kaushik4454

hi friend,
i also faced this problem.
sol-1
provide a gap between vessel nozzel and radar flang to
exhaust the fumes
sol-2
to avoid get in touch with the fumes arrange one small air
purging at antena.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the GK Value in Flowmeter?

3060


Regarding , there is an air cooler which control the fans(50% of AV FANS) by temperature in outlet , and the louver of Air cooler is controlled by HIC from control system , So if on Air cooler we will consider 2 individual I/P converter or positioner?

1369


Boolean algebra

1721


what is actual drum level and compensated drum level?

1773


principle of dead weight tester ?

1608






Why ac supply load cell is used? Can we use the dc supply load cell?

606


why we should maintain neutral earth voltage below 1V while calibration? why cant it be 1.2V or 2V

2005


WHAT IS THE CAM POSITION IN CONTROL VALVE POSITIONER ? WHY IT IS USED?

557


i want formula for flow control.am doing project in flow control using orifice . i know value of the flow level(Q) . upstream(p1) pressure, orifice diameter(Do) , pipe diameter(Di) and oil viscosity(Vi) how can i calculate downstream pressure

1454


hello sir/madam, I,Subramanian need 5yrs placement papers of officer trainee of Instrumentation technology.pls send to this mail id mani_nxtgen@yahoo.co.in please do the needful. with regards, subramanian.v

1773


what is basic difference between motion balance and force balance in pneumatic instrument?

8961


I m appointed as an automation trainee engineer in small firm in that I am only the one , my company give me a project on s7-200 as i m beginner I don't know how to program so please send me the helpful site so that I complete my project before deadline....please help me out in this critical situation.

1578


Isometric drawings are generated during _________________ phase of a project

1619


please tell no. & add. of consultancy who recruit me in power plant as instrumen engg. present i m working in power plant as ass.t instrument engg. thanku mahesh 09226562826

1638


Please any one can provide latest aptitude test,technical test and interview questions for tata consulting engineering (TCE) i need it asap thanks in advance

1559