how much cement and sand is used for plastering 1646 sq
feet,for 12mm thickness and ratio 1:4
Answer Posted / vinod
Cement = 16.82 (=say 17 bags)
Sand = 2.348 Cu.m
| Is This Answer Correct ? | 9 Yes | 5 No |
Post New Answer View All Answers
How much for the BRC lapping in full yield and half yield < and which table to get it ?
Will going from a 3-tap to 6-tap increase water pressure?
give me the mix proportion for design mix concrete M 7.5 grade 1:4:8
in block masonry l=10',b=0.5',H=10',Calculate cement ,sand and no.Of blocks?
How much cement will require for 1Rmt Skirting laying
what is SDLC ?and write a 'c'program for to swapping the three numbers?
what is tension footing?
What is the difference between EPC,DBOOT and BOOT.
to minimize budget cost of building , what can i do
Prepare a Schedule for a Highrised building from starting stage to Handover?
How to calculate the cement consumption in RR Masonry in CM 1:8 for the foundation of Ground Level Reservoir
sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.
Explain the benefits of using standard terminology in the measurement process?(Tendering and estimation)
What is the frequency of sampling for the materials of cement,Fine aggregate, Coarse aggregate .and refer which code
how to calculate the scour depth