1)What is swear, swage and storm water?
2)What are the sizes of bricks based on Nominal, practical
and standard?
3) What is the distinguies between the grade of cement 43,
53?
Answer Posted / sreenu b
1 Sewer is the structure which is used for the purpose of
disposal/flowing of Raw water
Sewege is the waste water coming from w/c or such dirty
water with bad smel
2 standard-19cmx9cmx9cm
normal-20cmx10cmx10cm
3 1. Fineness of cement. 53 grade fineness compare than to 43
grade cement.
2.compressive strength of concrete.
3.Low content gypsum so, 53 grade Fast Harding compare than
to 43 grade.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
five benefits of using standard terminology in the measurement process
What is the quantity of cement used for stone pitching work of 100sqm 225mm thick and cement mortar of 1:6? And how?
A roof has a U value = 0.65 W/m2 .C. Extra insulation is to be provided. This insulation has a thermal resistance = 1.5 m2"C/W. Calculate the new improved U value.
significance of specific surface area of particles?
How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
why we provide bent up reinforcement bars at l/4 ? if it is because of diagonal shear , how does it acts ?
For making a new road in a village having a school & hospital , tell the steps of construction systemically ?
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation
What tor stands for in tor steel?
How to calculate plastering for elevated water storage tank
What is the difference between undo & redo?
Can we use concrete of slump cone in cube casting in which we have already measured slump?