Calculate the quantity of concrete for the following.
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.
Answer Posted / ranjithkumar
pile dia is 0.3m,
so, radious is 0.15m
quantity = 3.14*0.15*0.15*10
= 0.706
2 under reamed pile
so,
0.706*2
= 1.414 cubic meter
| Is This Answer Correct ? | 6 Yes | 17 No |
Post New Answer View All Answers
115mm thickness brick work how to required mortar
how we calculate the grade of the Bituminous materials.?????
what are the grades of concrete?where and or what purpose a particular grade is used in a particular structure?
What is the value of live load that should be incorporated in design of locker room and cash vault room while designing a building for commercial bank?
How much cement,sand,bricks and water needed for 1square metre brick work?
The largest size of paper used in plotter to print the drawing made by Autocad .
how beam.coloum ,slab, footing are designed as per indian code.. detail procedure?
explain fie benefits of using standard terminology in the measurement process
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
I am practising engineer. I am searching for tutorial of RCC T Girder design Example in staad pro.Do anybody has this?please help
what is anchorage length,lap length and (dont remember the last one)
Name the main components of a cad gui?
how many litres of enamel paint required for 5000 sft of site??
how gradation of aggregates effect on slump of fresh concrete?
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks