What is the wastage % of concrete in Conventional
shuttering design & Mivan Shuttering for high rise building.
Answer Posted / s
6% of concrete in conventional & 3.5% in mivan
Is This Answer Correct ? | 7 Yes | 0 No |
Post New Answer View All Answers
What quantity of 1.0 m3 bricks required?
What is the strength of cement?
what is mean by c32/40s concrete class
For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?
What are some structures that may be subjected to fatigue?
What is the density of 1:1.5 (Cement:sand) ratio in plaster? And Conversion in 12.5 mm thickness per square meter? Howmany Kg of Cement square meter in ratio of 1:1.5?
Explain the difference between shear and tensile strength.
we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level
How to calculate the quantity of ingredients of M20 grade concrete?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
how to calculate load for a bungalow and 1column carry how much load if the size of column ,9"*15" .....or total structure load......
How cracks in concrete can be avoided?
What is the minimum size of the particles of silt soil?
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?