if compressive strength on 28day pass, and client is asking
core test. is there any thing in standards allows that??
Answer Posted / ramesh potaraju
if compressive strength on 28 day pass.
but that will not reached TARGET MEAN STRENGTH .
That's why client is asking for core testing
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
how many type of admixtures for water stored structure?
how much cement and sand required for 1cum rr masonry
How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.
WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
How to check slab shuttering level.? Or check list for slab ?
five benefits of using standard terminology in the measurement process
What is the formula for figuring out how many gallons of water are in a pipe by the foot?
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
how to control PQI (Project Quality Index)
What is the material consumption- cement,sand,tiles etc for Toilet dado?
What is meant by solid geometry?
how to prepare site mix design
what could be the production cost of 1 cum of concrete by CP30 plant