Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Boiler capacity is 5ton, what will be the feed water tank
capacity?

Answer Posted / d.sudhakar rao

If boiler capacity is five tons the feed water tank
capacity shouls be 4-5 times of the capacity of the boiler,
20 Kl to 25 KL is required.

Is This Answer Correct ?    4 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

some one can tell me how residual type excitation is provided through transformers to an AC generator without any battery or PMG&excitor

2351


Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.

3369


How We Calibrate the vaccum transmitter?

1928


dear sir i have completed one year post diploma certificate in thermal power engineering from national power training institute durgapur ...plz suggest me for power sector job

2489


why is the in steam turbine axial displacement of active side thrust pad is positive and non active side thrust pad is negative.

3185


what is restricted earth fault explain in details

1996


why do you consider yourself a suitable candidate for this position

7385


what is the basic use of power plant in equipment

1673


explain how the third harmonic content of the magnetising current affects transformer design

3209


procedure of how to generate power in solar plant.

1901


im try to calculating seawater flow required for SW-FGD system. I need a guide, equation or method to do it, can some one help me! Thanks very much

1936


Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon

2417


can u please tell me how to calculate the concrete quantity for a under reamed pile? r=300mm,depth=3m for a cylinder and for bulb l=.750mm,width=.525

1692


How to calculate boiler capacity? I have 1 Autoclave, Which has to use for AAC block. Dimension for this Autoclave is - 13 Meter Length & 2.2 Meter Diameter.

2242


How do you consider that you can improve and what assistance do you need to achieve this

1707