Calculate the quantity of concrete for the following.
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.
Answer Posted / bharath m,+91 8438238335/99806
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.
Solution :
(Pls. refer construction practice book & IS 2911 Part-III.)
2 under reamed pile means there are 2 Nos. of bulbs at particular spacing based on friction of soil.
Dia. of pile : 0.30 m. ie.,bulb dia. = 2.5 times dia. of pile
So it is 2.5*.3 = .75 m.
Length of Pile = 10.00 m.
Bulb thickness at pile intersection end (30-45degree inclination)= 1.75 times pile dia.
=1.75*.3
=0.525 m. &
free end = dia. of pile/4
=.3/4
=0.075 m.
Now follow the calculation:
Step 1:
Pile volume = Area x length
3.14/4*dxd x length
=3.14/4*.3*.3*10 = 0.707 Cubic Metre. ------1
Extra for Bulb Volume = Perimeter x Depth of bulb
=2*3.14*r x db
r at centre line of bulb = ((.75-.3)/2)+.3 = 0.525 m.
V=2*3.14x .525x(.525+.075)/2
=0.989 Cum. for 1 Bulb
V for 2 Bulb = .989*2
=1.978 Cubic metre -----2
Now combined Total Volume of Concrete 1+2 = .707+1.978 = 2.685 Cubic Metre.
| Is This Answer Correct ? | 44 Yes | 53 No |
Post New Answer View All Answers
Define a polyline?
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L
What are the advantages of cad?
What tor stands for in tor steel?
How to calculate cement and river sand material Qty for waterproofing base coat and finish coat
how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?
What is the difference between built area and super built up area?
What materials were used to build the golden gate bridge?
What is the maximum strength of cub compress strength in one cub testing
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
How to design staircase.plz tell me formula for the design the staircase.
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
How to calculate the cement consumption in RR Masonry in CM 1:8 for the foundation of Ground Level Reservoir
what is pouring and explain