Calculate the quantity of concrete for the following.
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.
Answer Posted / gopi
(3.14*0.3*0.3/4)*10=0.7065m3
Is This Answer Correct ? | 19 Yes | 21 No |
Post New Answer View All Answers
What black man invented the clothes dryer?
The 4 main factors to start a construction project are––
what is the meaning of 40/20 src
How to calculate quanty of steel in four leg stirrups?
How to determine thee cut length for steel reinforcement bars in R.C.C design
Explain what is 1/8 on the architect ruler denotes?
How to calculate quantity of plum masonry in 1:3:7
What is the effect of a building collapse?
what is total volume of ingredients used in concrete accordingly
WHAT DLC DESIGN IN CONSTRUCTION
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
cause of cylinder test failure
how to do cementicious paint for rcc walls of cw pump house
What is difference between code and standard and specification?
What is Architect-Prepared Contract?