Calculate the quantity of concrete for the following.
2 Under-reamed cast in situ pile of 300 mm dia. of 10.00 m
length.
Answer Posted / lisy rajan
Quantity of concrete= 2* 3.14*.15*.15*10=1.413m3
(with out deducting steel)
Is This Answer Correct ? | 4 Yes | 12 No |
Post New Answer View All Answers
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
need to join coaching institute in coimbatore tamilnadu ......say me the best coaching for IAS
Whats be the minimum foundation depth of multistoried building as per height of building in individual footing?
What is the ideal size of the living room ranges from small to large size?
Calculation of curtain wall of box culvert
What is the thickness of slab for 600 sq each) 2 slab construction. What should be the size of steel rod?
Is it necessary to apply tack coat over the primecoat. IF not what happens.answers other than 1.to superimpose the next layer(2) to adhere the layers so as to form homogenity.
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
material used for mendrel use to bend epoxy coated rebar
what is BPM in concrete demolition hammers. what is better a higher value or lower
I need old MMUP exam question and answer for Civil engineering
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
Please tell me vasthu room sizes. Thanks.
what is the theoritical percentage of concrete cubes testing per day?