Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

I have a 5KVA UPS. Total load to be connected almost 3KW.
Ordering a battery pack with capacity of 1920VAh.

How long will the backup time be?

Answer Posted / vijay

38.4mins backup time

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Why HT 11 KV Slipring Motors are connected in star ?

2275


what is the concept of directional power?

2092


primery try cell?

2254


WE HAVE THE DC RECTIFIER 1500A, INPUT VOLTAGE IS 3 PHASE. HOW TO CALICULATE THE LOAD? 3 PHASE SIDE EITHER dC SIDE. PLEASE SUGGEST ME

1930


HOW TO CALCULATE CAPACITOR BANK OR HARMONIC FILTER CALCULATION

2384


why does make gain margin and phase margin on same plot.?

2183


I am a possesor of c licence from 1993. I forgot to renew during the year 1998. During that time I was working at TNEB to till date. Is there any possibility to get renewed? or to apply for a new one?

2082


what is fault level of power system ?

6483


In case of generator when we consume more power produces by it why load on generator increase and starts sound more. and how it is adjusted..

1990


what is residuel magnetism. and how order lead acid batteries for 24 volt. emergency lighting system.

2056


Define active filter?

1084


A generating system will have a total capacity of 300 MW. Find the probable forced outage when the capacity is supplied by two 150 MW units. The operating probability of all units is P=0.98 and forced outage probability rate Q =0.02 .

2686


what is the effect of un-synchronized power.

2113


Why in power plant projects we see DOL starting method used for motors upto 160 kW instead of star delta method

1901


all details of DG UPS HVAC

2136