why we do multiply 1.54 for dry volume of concrete?
Answer Posted / hidayathulla
First your question is wrong. how ever
for one cum:- ADD 30 to 33 % dry volume Because the volume will reduce after mixing water.so that we add that %. and
for one cum:- ADD 20% of wet mortor for wastage,Uneven surfaces ect.
there fore for one cum :- 1+0.3+0.2 =1.50 to 53.
we can use this at the time of material requirement ect.
Is This Answer Correct ? | 62 Yes | 17 No |
Post New Answer View All Answers
what is the cost of rcc roof casting of 400 sq. ft. in kolkata
what is the minimum cement content for M20 & M25 as per is code -456(2000).
how to calculate mivan shuttering matrial
Define What is the best type of wood glue?
Why should you show Client/Engineer activities clearly on the project plan?
what is the permanent solution applied for restoration of leaning tower of pisa?
can any one tell me in detail footing estimation .. i am new here in dubai so facing lots of problem...
How to fix toll charge for a particular vehicle at toll booths in a highway?
Which are the top apps for you civil engineer?
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
Technical Question of Civil Engineering
i just want to know how much require sand and cement for 1 sq.mt including wastage. Please guide me as soon as possible.
What is the snap size in civil and how can we create it?
What is hybrid foundation?