How the Delivery date is determine in third party sales
order? If delivery date changed in PO, it should get updated
in order also. what are the settings required in third party
sales order?
Answer Posted / navin kaluti
n this type of scheduling, the requested delivery date is
given. Based on this date, the system calculates all other
dates such as the purchase order creation date and loading
date. To calculate the dates, the system uses the known
times for the individual activities such as loading time or
transportation time.
The calculation of the individual dates is a prerequisite
for all dates being able to be adhered to. If the dates are
adhered to, you can ensure that your customer receives the
products on the requested delivery date.
Scheduling based on the requested delivery date consists of
the following steps:
...
...
...
1.Requested delivery date plus unloading time
Based on this addition, the system calculates the unloading
date.
2.Requested delivery date minus transportation time
Based on this subtraction, the system calculates the goods
issue date.
3.Goods issue date minus loading time
Based on this subtraction, the system calculates the loading
date.
4.Loading date minus pick/pack time
Based on this subtraction, the system calculates the
material availability date.
5.Loading date minus planning time
Based on this subtraction, the system calculates the
planning date.
6.Material availability date minus order processing lead
time of supplier minus order processing time
Based on this subtraction, the system calculates the
purchase order creation date. The purchase order creation
date refers to the latest date on which the supplier should
receive the purchase order.
7.Purchase order creation date minus purchase order
processing time
Based on this subtraction, the system calculates the latest
possible sales order creation date.
The following figure illustrates the process steps that the
system performs when it executes scheduling based on the
requested delivery date.
Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
We want to explode bill of material automatically at time of order entry and explode an equipment bom in the sales order. What are the setting required?
Steps of tax determination?
What sap systems have integration capabilities with sap transportation management? : transportation management
what is the main purpose of maintaining the master data?
Tell me a customization which you have done & worked for your client which is not in standard SAP settings? Explain the requirement along with detailed procedure & process,t- codes if any from your real time data in your project? This question is most frequently asked in many interviews.Please reply asap... Urgent!!!! Waiting for your response eagerly... Thanks in advance
What is the transaction code for creating a material in sap and what is the transaction code to extend a material?
Define Product attributes?
What is higher level item category?
Can you split deliveries into several invoices? When would you do that?
What is the function of Profit center in Material master and how will system react when it finds Profit center in MM/when it does not find Profit center in MM? Plz answer for both the scenarios?
What is the parallel and local currency in sap?
When we include a new customer, we have to maintain condition record every time or there is a process by which we can validate the condition record to that new customer belonging to the same sales area?
client wants to have sales of particular material area wise. How to write functional spec for this
Explain how you can include condition type in the pricing procedure?
What are the effects of posting goods issue? Explain.