Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Pl let me know approx. Rcc construction cost per sq.Foot for
Building a house with2800 sqfeet carpet area in pune city

Answer Posted / patil

Excavation & filling :10/sqft
RCC cost : 450 /sqft
Brickwork & Plaster : 325 /sqft
Flooring & Dado : 100/sqft
Water proofing :50/sqft
Door : 80/sqft
Window : 75/sqft
Fabrication work : 30/ sqft
Paintng :20/sqft
Plumbing : 75/sqft
Electrical : 80/sqft
____________________________________
Total : 1295 say 1300/sqft

Is This Answer Correct ?    58 Yes 19 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.

3262


What is the release of lien?

1125


Curing time for 1)R.C.C slab 2)B.W 3)Plastering

2023


how to calculate the weight of concrete

1553


What is thumb rule in quantity and cost estimation of a residential building?

3066


how can calculate cutting length of diamond ring

1772


rate analysis for cement pointing 1:4 , for 100 sq m

4124


 Which Types Of Bricks ? 

2951


pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer

3037


how to estimate material requirement for an area of house in square feet?

2261


How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?

1765


What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?

2659


how to calculate the size of triangular ring in rcc column?

1758


What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.

2019


I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?

2335