how can we calculate the cooper armed cable size if the
protection load of main fuse is 80 ampere.
Answer Posted / anik misra
Though selection of cable is totally depends on
distance,load and type of media.But as a thumb rule we can
cay that
For Cable, Amp Capacity of Cable = 4X Size of Cable (Sq.mm.)
so as per question approx.(80/4=20)20 Sq.mm. cable required.
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
How much costly in percentage wise is sandwich busduct costly than air insulated busduct of any rating?
Why sometime AVR and sometime Booster coil is used in Alternator? what is the diferance between AVR & Booster coil due to which they are selected
Why mostly the HV side of transformer has Delta?
I have experienced electrical maintenance HT ,but I completed be ECE ....can I apply c license or not ???? Pls help me friend s...
what is the difference between earth leakage and earth fault?
whate is the meaning of balance/unbalance,in stabilizers type
howmany electrician should maintain for a 1000 kva used plant... in kerala..
what is plunger and what's the use of it in motor alignment?
what are the different sizes of U.G. cable & where these cabl;es are used according to voltage ..
what is solkor relay and which condition it will act?
what is the safty of poly phase tranformer?
when generator short circuit condition, the current how dissipates. or at short circuit voltage not available then current how can flow?
Can we test the alignment of End shield and stator of turbogenerator without rotor insertion? Also how to fix maintain the alignment at site installation?
HOW TO WRITE A QUENTION ANSWER? I MEAN SHORT OR LENGHTHY ? OR FROM THE BOOK AS BOOK..... SOME TIME WE GIVE A ANS FROM THE BOOK AS LIKE BOOK ND WE GET MINIMUM 60% MARKS OR MORE THEN....... THEN HOW TO FILL THE Q-PAPER?
I have a situation to design sub-Distribution board/Panel meant for feeding power sockets. In the incomer CAN i Take TP MCCB with Neutral Link and All the outgoing feeders with to sockets with TP MCCB and Neutral Link? P.S : My System is IT Earthing