FOR FOUNDATION 50KG PER CUM
FOR SLAB 80KG PER CUM
FOR BEAM 110 KG PER CUM
FOR COLUMN 160KG PER PER CUM
FOR WALL 80 KG PER CUM
FOR SHELVES 80KG PER CUM
FOR STAIR CASE 100 KG PER CUM
| Is This Answer Correct ? | 24 Yes | 4 No |
Post New Answer View All Answers
Can compresive strength test for concrete at 1 day age possible to carry out? If yes, which IS code describes the procedure for such testing?
how calculate the bearing from two coordinates?
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
what is that one cub metre plaster in cemant and fine sand
I what know about life time of frp tank plz explain about it specifications & other details
where can i get the previous question papers for rrb section enginerr (civil)
What is unit weight of normal concrete?
what is the proper procedure in conducting a california bearing ratio penetration test on soil on cbr machine?
construction workers how much time take one work or qty
what is the water cement ratio of 1:6 and 1:4 cement sand mortar. reply soon
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?
How many pyramid in egypt?
at which depth the construction of tunnel is economical from cost and engineering aspect.
How to check slab shuttering level.? Or check list for slab ?