If the scenario is''Party is supplying some material we
have to do the some processing operation on it, how it cab
be handled in SAP"
Answer Posted / ajit kumar santi
You have to use Sub-contracting in MRP-2. proc type-F and Special proc type-subcontracting
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
How requirements( pir,sles order, customer requirement) are reduced after they are produced?
Mention what is the difference between stock transport order and stock transfer order?
Are there any reports in sap to list of material requirement from ltp ?
Differentiate ‘variant bom’ from ‘multiple bom’?
What are the types of master views for production and planning?
Which tool you are using
What is process keys
Explain service level agreements
Define ‘bom group’?
Different types of Object Dependencies.
How can you get planned orders scheduled so that you can do capacity leveling ?
In lsmw which is most important step?
How do I find which is the recurrent item in a production order? In the missing material analisys I got message MF 331, but the BOM or the production order don'thave any recurrent item Thanks
What is the planning time fence?
Explain DMR.