when we need to close the production order, before the
manufacturing or after the manufacturing
Answer Posted / ajit kumar santi
Goods movement can be posted in TECO status, but in closed status it can't and goods receipt is made after production. so close production order is made after manufacturing.
| Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
What is the use of mrp list?
How do you get the system to update this value from the routing?
What is purpose of schedule margin key?
Explain how ‘pp’ is ‘integrated’ with other modules?
Explain schedule margin key
Explain PI sheet.
When you run MRP, What steps it Perform in Back ground or How do you schedule BG job for MRP
Question related to Production order status or status profile?
what is the major ticket in your experience
what do you mean by planning time horizon
What are the parameters are there in Order type or in dependent para. config?
We have a lot of size procedure here which is creating more order proposals. How do you set the limit value for the maximum number of mrp order proposals per date in img?
What are gaps? Some examples?
suppose we have sales order-40, PIR-25,warehouse stock-40, so when we run mrp,what quantity the system displays with MTO & MTS. How?
In implementation stage tell some standard scenario before AS-Is & TO-BE