relation bet Coefficient consolidation Cv, time factor Tv,
drainage path d, & time t is
Cv=d2Tv/t
Cv=d2t/Tv
Cv=tTv/d2
Cv=Tv/td2
Answer Posted / nawal k dwivedi
Its first one i.e Cv=(Tv)(d^2)/t
| Is This Answer Correct ? | 13 Yes | 1 No |
Post New Answer View All Answers
what is the effect of duration of earth quake on framed structures ?
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
Describe Briefly The Various Methods Of Concrete Curing?
what is stressing
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
How to arrive d*d/162 , for finding the kg per meter , wt of steel
resins are not soluble in water soluble in spirit used in varnish left behind on evoporation of oil
Would you cause a 55-gallon drum of water to weigh more by climbing in?
why we are useing plastic under the lean concrete?and whts the advantage?
what is mean by reestimation?
Why is the use of granular sub-base in concrete carriageways not preferred, explain?
What is the difference between yeild strength and compressive strength of steel???
I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,
what is right & short method of measurement of slab&beam
what is the type of earthing