Concrete Mix designs for M15,M20,M25,M30 and M35
Answer Posted / sabir
M20=50-138-185 (kg) 22.5ltr water
M25=50-105-147 (kg) "
M30=50- 81-120 (kg) 21ltr water
M35=50- 70-140 (kg) 19ltr water
M40=50- 66-116 (kg) 17.5ltr water
| Is This Answer Correct ? | 22 Yes | 2 No |
Post New Answer View All Answers
what will happen if one could not properly follow the spacing of slab reinforcement bar?
How is make concrete cube?
what is the procedure involved in preparing mix design of m15 grade as per IS-10262-1982
which are the Indian auther books for STONE COLUMN/GRANULAR PILES?
How many square meter can mason layout chb per hour
How much cement and water required for cement selery????
For a washout valve why are two gate valves required in normal practice?
I want to join bhel because
What is .Dwg?
What are the joints wants to made in masonry where door opening, arches like etc..
In csae of hume pipes NP stands for Non Pressure bur what does it really mean?
What is the crank length in the slab?
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
Discuss some applications of modular elasticity?