In RTU Panel we are having several Analogue & Digital
Inputs /Outputs. We are recently facing some problems over
Analog inputs , which are not updating properly (But
Digital Input are updating normally) Can any one tell me
from where the problem is creating , we have checked PLC
CPU card, Analog Input card & we reconfigured ,But still
the issue is there.
Issue :
1. Sometimes Analog values are updating & sometimes not.
2. Analog values are not updating normally , showing some
wrong Values
3. Total dead (0 value)
Analog values are Level & flow measurement from the field
instruments.
(But in field the instruments are working normally &
Displaying the values normally in local display unit)
This problem we are facing in our Water Plant.
If any one experienced this same problem or having any
ideas related to our issue PLS send your valuable
Answers/Replies...
Answer Posted / manunath
hi....
there may be chance of two problem
1.problem with scaling of signal or
2.check the system earth ie AI module earthing...some
time it will create problem..
thank u
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
why any measurement made interms of pressure is more accurate ? to be more precise most of the flow velocity is made interms of pressure and it is accurate. what is the reason behind pressure measurement being accurate ?
What is Cavitation in a control valve?
send me HPCL paper
Which tank weighing system is better to install (Accuracy point of view) 1) Tank weighing system with 3 load cell or 2) Tank weighing system with 4 Load cell
what is the reset offset and control system in instrumentation
Linear amplifier.
what is temperature compensation?
what is commisioning procedure,2)what is is the main work in commisioning in the field tx to dcs, plz send me detail
how to calibrate Necleuonic level transmitter.?
What are the interlocks we have to check during the start up of LP/HP compressor?
how to calibrate and troubleshooting of leveltroll?
how do calibrate the valves.. with clear manual
Isometric drawings are generated during _________________ phase of a project
plz tell me clearly about PID.."when v have to change I value,D value,GAIN??
Can any one tell me what type of question asked for instrumentation and control interview panel??? pls mail ramashankar.goel@gmail.com