Providing and fixing in position Tor steel to footings,
foundation, slabs, beams, columns, canopies, stair case,
newels, chajjas, lintels, etc. including cutting, bending,
hooking the bars, binding with wires. give me the rate M.ton.
Answer Posted / shabu
in jan 2013-the rate is 5500/tonne
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
Calculate the maximum allowable speed on a horizontal curve of radius 350m if the maximum allowable values of the lateral coefficient of friction are 0.14 and the rate of superelevation is 0.08.
What is hybrid foundation?
why we create short columns under grade slab?
how we check the thickness and line of ceiling plaster.
Define What is aggregate?
How much quantity of rod binding work by a rod binder per day
How to do rate analysis for concrete work including shuttering work?
within an emergency scenario what are the safe systems of work a coss can setup as part of is duties
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
How to calculate carrying capacity of the existing water supply trunkmain
how many litres of enamel paint required for 5000 sft of site??
what are the types of design? which type of method is used at what type of design & why?
What is OSHA compliance?
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
what is the function of GSB all class ?