Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how shall you calculate PLF on the basis of percentage auxillary load factor

Answer Posted / gajanan kuhite

PLF is nothing but the plant load factor & it is calculated
by following formula

%PLF = avg.load/total installed capacity *100

Is This Answer Correct ?    8 Yes 8 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Which will have more strain energy 1.Spring 2.Circular disc 3.Solid square plate.

2356


what is restricted earth fault explain in details

1992


what is the trip circuit supervision in an electrical meaning?

2026


what does mean by kva rating

1440


Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.

3366


procedure of how to generate power in solar plant.

1897


what is the difference between compensated & normal drum level in boiler drum?

1738


why airtel use + 24 volts and other operators use -48 volt

2565


how to differentiate between "ALL fuel lost" and "All Fuel Lost" in Boiler MFT condition?

1652


How to calculate power press toneage

2006


By any way can we increase the B check hours from 300 to 500

2142


can dp type level transmitter work in under vaccum condition

1941


what's the moog valve

1434


what is the meaning of SST300 V56A in SIEMENS turbine

4301


Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon

2411