How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / farvaris kumar
brick = 480 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .255 for one cum
Is This Answer Correct ? | 58 Yes | 27 No |
Post New Answer View All Answers
If specific gravity of cement is less than 3.15 what is the cause?
How will be cutting in timber plate size 600*400 column size
sir how can we find the cement and sand required for making 4" drop
a rectangle grill of length 72 inch x 20 inch width.how to calculate bar spacing ,bar consist 8 mm thickness and spacing of bar is 2 inch.. calculate no of bar with formula
how find the cut length of tringular ring and any formula find out the quantity of circular brick work
What is the quantity of cement in mix m20 concrete?
define the strength
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
what is Brick crushing strength(PSI)?
in the construction of residential building what type of tank are used?where?why & what is its purpose?
what is stressing
What is the distance between railway tracks?
what is castigliano theaorem
why +1 to be followed for calculating the no of bars in BBS. Please explain
important question on stones