How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / farvaris kumar
brick = 480 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .255 for one cum
| Is This Answer Correct ? | 58 Yes | 27 No |
Post New Answer View All Answers
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??
WHAT DLC DESIGN IN CONSTRUCTION
how to identify the failure of building by expansive soils
Differentiate orthographic and isometric projections?
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
What is the difference between shear and tensile strength?
What are the responsibilities of a site manager?
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
How to calculate concrete in percentage wise ,for example cement 18% sand 40% aggregate 40% and Stell 2% ,I need and??
what is w/c ratio in dry lean concrete for m10 mix design
I want to change job.If You have any vacancy please contact me in this mail id-parthamitra086@gmail.com.Myself partha mitra.Diploma in civil engineer with 4+ yrs. exp.Now in kolkata.If you confirm me then I will send my detail resume to you.Also send your mail id to me.My mail id is-parthamitra086@gmail.com.I will be very much thankful to you.
How to find out kg per Sft ?
Why is the use of granular sub-base in concrete carriageways not preferred, explain?
what is pouring and explain
What is the cost difference between site mix and ready mix concrete per cubic meter