How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step

Answer Posted / farvaris kumar

brick = 480 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .255 for one cum

Is This Answer Correct ?    58 Yes 27 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

If specific gravity of cement is less than 3.15 what is the cause?

1872


How will be cutting in timber plate size 600*400 column size

1245


sir how can we find the cement and sand required for making 4" drop

1650


a rectangle grill of length 72 inch x 20 inch width.how to calculate bar spacing ,bar consist 8 mm thickness and spacing of bar is 2 inch.. calculate no of bar with formula

1223


how find the cut length of tringular ring and any formula find out the quantity of circular brick work

5688






What is the quantity of cement in mix m20 concrete?

698


define the strength

1704


what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?

1670


what is Brick crushing strength(PSI)?

852


in the construction of residential building what type of tank are used?where?why & what is its purpose?

1910


what is stressing

5818


What is the distance between railway tracks?

698


what is castigliano theaorem

1835


why +1 to be followed for calculating the no of bars in BBS. Please explain

1513


important question on stones

1522