how many bags of cement,sand and Aggregate to p.c.c. of 1:2:4
ratio.
Answer Posted / vipin
325 kg cement,
.43 cum corse sand,
.86 cum aggrigates,
30 liter water
Is This Answer Correct ? | 3 Yes | 4 No |
Post New Answer View All Answers
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
What is proportion of PCC Grade G?
Forces in a Shear Wall are in plane or out of plane ?
What is the use of mirror command?
How much percentage of brick bats allowed in CD-75 bricks
insted of bentonite we can use any alternate material in piling ?
in one SQM plaster how much Cement and sand consumed in ratio 1:4
which steel is better for residential building tmt steel or hysd steel
How many mortar required for Brickwork of 1 Cu.m works??
Water filter calculation formula
What is hybrid foundation?
can you provide a link for manual design of building?
What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.
how to calculate the crushing strength of cement concrete paver blocks 100x100x60 mm thich.
What is the significance of cost estimate knowledge for an architect?