In site how we can identify one way slab and two way slab?

Answer Posted / silambarsan

For easy identification without calculation,In oneway slab
main reinforcement provided in the shorter direction and
distribution will be longer side.In two way slab Both side
main reinforcement will be there and mainbar also act as a
distribution bar.

Is This Answer Correct ?    41 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

please briefly explain calculating or estimating steel quantity for a RCC column?

1448


hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having

2047


Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?

2395


Explain the Strength of brick?

666


How to calculate Volume of Wet cement concrete for a specific grade?

1780






what is pouring and explain

1834


What is the crank length in the slab?

637


how to calculate quantity of cement,sand & aggregate for u.c.r / r.r masonry in cm 1:6

5801


pls give me ans to ACT formula cube testing porpuse

2549


How much the quantity of Dry material of Crush for 1:2:4 Concrete, using pan 3/8'' down....

1517


how can i calculate cement in brickwork

3472


How do we calculate absolute pressure?

779


I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

1650


what is the permanent solution applied for restoration of leaning tower of pisa?

3071


how we calculate the vol.of wet concrete..?

1417