Answer Posted / vidyasagar daley
EG:If you take 12mm thickness then caclulation to be done.
for 1cum 1:3 cement mortor then
we have to consider dry density and wet density.
wet density 50% to be taken more then actual quantity so
1x1.5=1.5cum,
1.5/1+3=0.375
1CUM CEMENT WIEGHT IS1440KG/CUM,
(0.375X1440)/50KGS(one cement bag wieght)=540kgs/cum.
| Is This Answer Correct ? | 2 Yes | 2 No |
Post New Answer View All Answers
what is the proper procedure in conducting a california bearing ratio penetration test on soil on cbr machine?
what is the basic difference between Coloumn & Shear Wall
How to calculate quanty of steel in four leg stirrups?
how to calculate valuation for the old building?
Which is the direction for positive angle?
TELL ME THE EQUATION FOR OGEE SPILLWAY
What is the density of DLC & PQC and how it is differ from normal concrete?
Which ratio use for cement selery???
How many bricks are there in 100cft?
Mention what are the composition of a landfill?
Where is the worlds longest elevator and how long is it?
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
load combinations how many types for staad design purpose?
Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions
on what basis the partial factor of safety are decided? form the load combinations