How to calculate cement and sand quantities in cement mortar
As 1:1,1:2,1:4,1:6 ?
Answer Posted / dilshad akthar
ratio: 1:4
for 1 m3,cement= 1/(1+4)=1/5=.2m3,let it be .2+.6*.2=.32
quqntity of cement:
.32*1440(unit wt of cement)*1=460.8
bags rqd= 460.8/50(1 bag)=9.2````let be 10;
sand requred
4*.2*1=.8m3
typical one load==5m3
| Is This Answer Correct ? | 0 Yes | 4 No |
Post New Answer View All Answers
What is the zero value in quantity surveying
What materials were used to build the golden gate bridge?
Gidc technical que paper
what is the difference between prime coat and tack coat in road construction
where can i get the previous question papers for rrb section enginerr (civil)
During reclamation how can the occurrence of mud waves can be rectified?
16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?
How to testing voids of filled aggregate in bitumen mix design
How many kilo-newtons equals 1000 kilogram?
How much quantity of cement,sand,stone used to build 1 cum of cc road??
brickwork labour rate per cum ?
usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?
What is fineness modulus ? and its sieve # ?
Hollow block masonry in cement mortar 1:4, 40×20×20cms in superstructure take 10sqm.I want calculation of brick sand